August 2021 Construction Updates

August 9, 2021

Gondola Terminal Move
The operator cabin has been installed. Lower terminal foundations have been poured and work on the retaining wall foundation is ongoing.

Base Area Improvements and Resort Entrance
The foundations for the escalator have been poured and the escalators will be set in place over the next few weeks. A new storm drain and snowmelt system is being installed in the plaza.

 

August 23, 2021

Gondola Terminal Move
North rock retaining wall is being installed. Electrical work is being completed by Yampa Valley Electric Association. Work is being done on the Burgess Creek Bridge.

Base Area Improvements and Resort Entrance
There will be a crane on site this week to assist in erecting the steel at the new resort entrance. Final concrete will be poured and the escalators will be set this week.