News / July 2021 Constructi... July 31, 2021

July 2021 Construction Updates

July 6, 2021

Grading work in the future Greenhorn Ranch learning area located near the Bashor Bowl will begin Monday, July 12. This will cause the closure of the Disc Golf Course for the remainder of the season and impact bike trails over the next few weeks. Stay up to date on the latest impacts on our website or Steamboat app.

Gondola Terminal Move

The canopy for the new gondola terminal will be installed this week along with pouring of foundations and footings for the site walls. Next week retaining walls will begin being installed.

Base Area Improvements and Resort Entrance
Materials from demolition continue to be sorted for recycling and hauled away. The demolition of the bridge near the Sheraton that will make way for the Gold Walk entrance continues.

 

July 13, 2021

Gondola Terminal Move
The walls started being built for the operator cabin this week. Foundations have been poured for a snowmaking machinery vault. Steel will be involved for an elevator that will service the lower terminal.

Base Area Improvements and Resort Entrance
Foundations for the future escalator are starting to be built. The demo work on the stage is complete and the demo of the stage is complete. Utility work for the under-plaza will begin this week.

 

July 27, 2021

Gondola Terminal Move
The splicing of the haul rope was completed last week. Work continues on the operator cabin for the gondola. Structural steel will be put in place.

Base Area Improvements and Resort Entrance
Demo of the Gold Walk topping slab is nearly complete. An end slab on the bridge near the Sheraton is being removed to make way for the future escalator.