News / June 2021 Constructi... June 30, 2021

June 2021 Construction Updates

June 15, 2021

Gondola Terminal Move
The underground mechanical systems for the lower gondola terminal have begun installation. Steel erection is slated to begin next week.

Base Area Improvements and Resort Entrance
Demolition has been completed for both the Gondola and SnowSports buildings. Clean up, including recycling and sorting of materials, will be ongoing for the remainder of June. Hauling of debris will continue through the month of June from 7 a.m. to 7 p.m. daily. The Goldwalk/Sheraton bridge demolition is underway and will connect to the future escalator that will be installed later this summer.

 

June 29, 2021

Gondola Terminal Move
Lower terminal foundation walls are being installed. New gondola towers for the lower terminal are being installed. Underground mechanical systems for the lower terminal are beginning to be installed as well as the mechanics for an elevator in the lower terminal.

Base Area Improvements and Resort Entrance
Clean up from demolition is nearly complete and includes recycling sorting and hauling of materials. The Goldwalk/Sheraton bridge that will connect the transit center with Gondola Square is being demolished and rebuilt, this work will continue through the end of July.

Do Not Sell or Share My Personal Information