May 2022 Construction Update

May 11, 2022

Steamboat Square/Base of Resort

  • The elevator core and Shear wall for The Range Food Hall is nearly complete. Structure of building will start to take place over the next few weeks.
  • Preparations are being made to the Christie Peak Express lift lower terminal for relocation.
  • Preview Lift has been removed. The mini golf course and mountain coaster/coaster building have been removed about halfway up the hill.

Greenhorn Ranch

  • A crane has been mobilized at Greenhorn Ranch to load in a large amount of equipment and materials. There will be heavy truck and machinery traffic over the next week. Keep an eye on the website for any temporary trail closures.
  • Excavation work has started for the Wild Blue Gondola mid-station terminal. The Bashor restrooms have been removed.

May 25, 2022

Steamboat Square/Base of Resort

  • Heavy timbers for The Range Food Hall will begin installation this week and will continue for the next few weeks.
  • The Stage will begin to take shape mid-June.
  • The lower terminal of Christie Peak Express has been moved to the grass while waiting to be reinstalled.
  • Major earth work and grading at base area continues for Wild Blue Gondola and Christie Peak Express terminals and new tower locations for Christie Peak Express.

Greenhorn Ranch

  • The sprung tent structure at Rendezvous has been deconstructed and will be relocated at Greenhorn Ranch for SnowSports School use.
  • Excavation of the mid-station terminal for Wild Blue Gondola and new location of sprung tent structure has begun.
  • Forms/foundations for mid-station of Wild Blue Gondola are starting to take shape.