News / October 2021 Constru... October 31, 2021

October 2021 Construction Updates

October 4, 2021

Gondola Terminal Move
Load test has been completed. Installation of pavers began this week in the queuing area for the gondola. The cargo elevator installation began this week.

Base Area Improvements and Resort Entrance
Escalators have been set and installation will continue over the next few weeks. Waterproofing of the escalator began and concrete for the stairs adjacent to the escalator has been poured. A canopy will be installed after stairs and escalators are complete. Pavers in the resort entrance from the Transit Center will be installed at the end of the month. The concrete “lid” is on schedule to be installed on the square for mid-October.

 

October 18, 2021

Gondola Terminal Move
Paver installation is complete. Installation of the cargo elevator began this week.

Base Area Improvements and Resort Entrance
Installation of the escalator will be completed this week along with the start of paver placement at the resort entrance. The canopy above the escalator will begin installation next week. Steel supports have been installed in Steamboat Square and will be followed by a concrete ‘lid’ and installation of 30,000 square feet of pavers.