News / September 2022 Const... September 15, 2022

September 2022 Construction Updates

September 15, 2022 Update

Steamboat Square/Base of Resort

  • Pavers, light poles, and fire pits are being installed in the plaza.
  • Stone work on the stage will be complete by the end of the month, roofing is scheduled to begin next week.
  • Concrete is being poured on the ice rink at the end of the month and will cure for four weeks. The railings will be installed after the concrete.
  • The deck for the lower terminal will be installed later this month and RFID gates will be installed mid-October.
  • The pull rope for the Wild Blue Gondola will begin installation next week.

Greenhorn Ranch

  • Interior framing, drywall, electrical, and plumbing work continues in the Sprung Structure.
  • Mid-station terminal work on Wild Blue Gondola continues and will be complete by end of October.
  • Greenhorn Ranch Express lift drive station enclosure will be built at the end of October and the pull rope will be installed in early November.
  • Work on magic carpet installation and snowmaking infrastructure continues.

September 2 Update

Steamboat Square/Base of Resort

  • Plaza snowmelt is being installed.
  • Pavers are being set and fire pits will begin to be put in place.
  • Light poles will be put in place in the next few weeks.
  • Footings and caps for the stage will be poured this week. Stone will be set in early September. The roofing will follow in late September and pavers after that in early October.
  • The railing on the Ice Rink will be installed beginning next week. A slab will be poured in mid-September.
  • Christie Peak Express towers will be assembled over the next few weeks. The haul rope will be installed in mid-September.
  • The lower terminal canopy for Wild Blue Gondola is complete. Tower installation for the lower leg will be complete this week and rope installation will happen at the end of September.

Greenhorn Ranch

  • Sprung Structure tent installation is complete. Electrical, plumbing, and interior framing has started.
  • Mid-station terminal work continues and will be complete in early October.
  • Work on magic carpet installation and snowmaking infrastructure continues.